Design, Supply & Installation

Design, Verification & Documentation

  • Design and configuration of PV arrays, inverters and associated electrical networks
  • Design and submission of all shop drawings and as-built drawings
  • Design and simulation of PV system models for performance verification
  • Documentation and submission of all safety documents for the duration of work

Supply & Installation​

  • PV modules and supporting structures
  • Grid-tied PV inverters with data logging
  • Balance of System (BOS), including DC & AC cabling and trunking, lightning protection system, protection devices etc, up to point of common coupling (PCC)
  • Reticulation of PV power to MSB

Testing & Commissioning

  • Testing, quality assurance and performance verification prior to commissioning
  • LEW (PV) submission and endorsement 

Operation & Maintenance during contract term

  • Daily online cloud-based monitoring with alarm notifications
  • System performance and generation report
  • Spot cleaning of PV modules
  • Preventive maintenance site inspection, including structural checks, electrical measurements and thermal scanning

Schedule Projection

Week 0

Confirmation of project

Week 1 – 10 (8 to 10 weeks)

Preparations

Engineering Design, Procurement, Authorities, Submission

Week 11 – 17 (4 to 6 weeks)

Installation

PV Structure, PV Panels, AC/DC, Electricals

Concurrent (8 to 16 weeks)

SP Commissioning

LEW, Endorsement, SP Application submissions, SP Testing, (End of Project)

Warranty & Maintenance

System warranty

  • 12months from completion of installation of system
  • Waterproofing warranty: 3 year (if applicable)

Maintenance

  • Twice per year
  • 2,400 SGD per year (free for first 2 years)

Equipment Warranty

Warranty

1st Year Power Output: 99.0% of rated power

PV Module

30th Year Power Output: 87.4% of rated power

Material Warranty: 12 years

PV Inverter

5 years

PV Mounting Structure

10 years